Industrial Manufacturing Plant Decommission

Project Details

  • Project: Plant dismantle, load and remove all remaining assets leaving plant completely empty.  Also, relocate the company-purchased assets to their respective plants from Massachusetts and Mexico.

  • Equipment used: Approximately thirty (30) truckloads of machinery and ancillary equipment were relocated to their plant in Plympton, MA and 10 truckloads of machinery and equipment were transported to a company plant in Mexico.

  • Location: Eastern Pennsylvania

  • Date: 6 Months (June 2017 – December 2017)

From Light to Dark

A large North American manufacturer of commercial lighting products closed their 400,000 sq.ft. plant located in Eastern Pennsylvania. Over the years, A&A Machinery Moving had been the long-standing rigging resource, handling much of the machinery and equipment within the plant.

Production at the plant ceased in Mid-October 2017, with a real-estate ready deadline set in mid-December. This timeline gave A&A Machinery Moving less than 60 days to dismantle, load, and remove all remaining assets within the plant, delivering the plant completely empty to the customer on-time.

Scope of Work:

In accordance to the project scope developed, A&A Machinery presented a comprehensive turn-key package, providing all labor, coordination, equipment, and material necessary to perform the entire project from start to finish. A&A’s turn-key package included the following:

  • Match-mark, tag, and disconnect all electrical wiring, panels, duct work, and utility piping
  • Mechanically disassemble and disconnect redeployed machinery and ancillary equipment
  • Coordinate all trucking and logistical needs for redeployed assets to other sister-company plants
  • Complete the relocation and re-installation of 30 truckloads of machinery and ancillary equipment, including electrical and mechanical reconnects, at the sister company plant in Plympton, MA
  • Provide a creative approach of standing two (2) 300 Ton presses in Plympton, MA plant without removing the roof, which other bidding companies could not deliver on
  • Provide an on-site 5-man crew to work with customer management team to sort work-in-progress and support other North American sister-company facilities
  • Partner with a national auction company to hold an on-site auction, which achieved a return on surplus assets of greater than fifty percent (50%); higher than expected
  • Handle one hundred percent (100%) of the rigging and removal of auctioned assets. A&A also coordinated all the transportation needed to haul large and over-sized purchased assets
  • Provide crew to remove all remaining scrap and clean all machining pits within the facility
  • Deliver the plant empty and real-estate ready in less than 60 days, meeting the customer’s deadline set for sale of the plant

Contract Value: $1,500,000
Calendar Length of Project: 6 Months (June 2017 – December 2017)
Percentage of Labor Self-Performed: 100%
Total Man Hours: 5,671
Total Truck Loads: 267
Total Recordable Incidents (TRIR): 0

Before Decommission

Prior to start of the project, twelve (12) other sister companies across North America were brought in to buy any surplus assets within the plant. Roughly sixty percent (60%) of the manufacturing equipment was retained by the other sister plants. A&A Machinery presented a turn-key relocation package to dismantle, coordinate transportation and install company-purchased assets at their respective locations across North America. The relocation of the company-retained assets started in early June 2017.

Phase 1: Relocation & Redeployment

A&A Machinery provided all rigging foreman, and craft professionals needed to relocate the company-purchased assets to their respective plants. Approximately thirty (30) truckloads of machinery and ancillary equipment were relocated to their plant in Plympton, MA. A&A project managers and logistics team were responsible for coordinating all truckloads of assets from Bristol to Plympton as project schedule permitted. A&A also staffed a rigging crew at the Massachusetts plant to provide necessary unloading, installation, and reconnects of manufacturing machinery and equipment.

Another 10 truckloads of machinery and equipment were transported to a company plant in Mexico. A&A provided a trucking solution where loads going to the plant did not need to be trans-loaded at the border, reducing the risk of damage to the customer’s assets.

Presenting a Solution by Not Removing the Roof

Some of the larger manufacturing equipment retained by the customer were two 300 Ton Verson presses. Other rigging companies who bid on the project informed the customer they would need to remove parts of the roof of the plant to stand up both presses. Experienced project managers of A&A presented a creative approach to stand both 300 Ton presses within the plant without having to remove the roof by using a hydraulic gantry system and tailing the load with a heavy-duty Versa-Lift.

Phase 2: Auction & Liquidation

Remaining assets not purchased and redeployed by the other sister companies were auctioned off. Our sister company A&A Machinery Sales partnered with national auctioneers to host a public on-site auction in the plant. Production at the plant ceased on a Monday and the auction was held on Wednesday. A&A Machinery Moving was named the exclusive rigger of the auction, handling 100 percent (100%) of the removal of auction items to ensure meeting the customer’s deadline set. The auction achieved a return on surplus assets of great than fifty percent (50%), higher than expected.

Over four hundred and sixty (460) pieces of equipment were included in the auction. The largest piece sold and removed at the auction was a 500 Ton Verson straight-side press. The press and supplementary equipment weighed over 460,000 lb. collectively, with the crown of the press weighing 110,000 lb. The 500 Ton press required eight (8) truckloads to relocate the machine and ancillary equipment to a sister-company plant in Mexico. A&A’s trucking solution to avoid trans-loading at the border reduced any potential risk of damage to the 500 Ton press.

Phase 3: Real-Estate Ready

Assets sold in the auction could be removed from the plant starting the morning after the auction. To create a more efficient auction item removal process, A&A Machinery Moving provided an on-site estimating team during the auction for buyers to receive quotes for the rigging, removal, and transportation.

All assets, ancillary equipment, and miscellaneous materials were removed from the plant in less than 60 from the auction date. A&A provided an on-site crew to remove all remaining scrap and clean all pits within the facility. The Bristol plant was delivered empty by A&A Machinery Moving to the customer by the real estate-ready deadline set. The turn-key package presented by A&A Machinery Moving was a success for the customer and the plant decommission project. The long-time customer of A&A once again discovered the A&A Difference.

This project won a 2018 Associated Builders & Contractors Excellence in Construction Award in the Specialty Rigging Category

GVMA Compressor removal by A&A Machinery MovingRemove Two (2) 3,000HP Cooper LSV-12 Engines w/KM-4 Gas Compressors
Prefab Concrete Building RiggingElectrical Contractor Rigging Support – Prefab Building Turn-Key Install